Your DAS throws an alarm at 2pm: string 14 on inverter 3 is pulling 30% below its neighbors. That's a real finding. It's also where the useful information stops.

SCADA is built to watch amperage and voltage at the string or combiner level, around the clock, with no added cost once the data acquisition hardware is installed. A thermal flyover does something SCADA can't do on its own: it looks at every cell on every panel, once a year, from the air. Both have a job. Neither replaces the other.

What continuous SCADA monitoring catches

String-level and inverter-level data acquisition systems are good at exactly what they're designed for:

  • A string that drops out entirely (tripped breaker, blown fuse, a connector that let go)
  • Gradual underperformance on one string relative to its array
  • Inverter faults, ground faults, and communication loss
  • Production shortfalls against an expected-energy model, usually caught within a day or two

None of that requires a crew to set foot on site. That's the appeal. A good DAS will tell you string 14 is underperforming today, not six weeks from now at the next scheduled walk.

What it won't tell you: which panel on string 14 is the problem, or whether the string is fine and the real loss is five strings over, where soiling has built up on the low row and nothing has failed hard enough to trip an alarm. SCADA aggregates. A single cracked cell, a failed bypass diode, or a junction box running hot can sit inside a string that's still producing "close enough" numbers to stay under the alarm threshold for months.

What a thermal flyover catches

A GSD ≤3 cm thermal pass, flown by drone or crewed aircraft, is looking at the array the way a handheld thermal camera would if you walked every row, except it actually covers the site in one pass instead of three days of a tech on foot. Paired with RGB at the same resolution, it catches:

  • Hot cells and hot spots inside a module, cell-level, before they've degraded output enough to register on a DAS
  • String outages and bypass diode failures, including ones buried inside a string that's still clearing the alarm threshold
  • Soiling patterns across the array, which show up as uneven thermal signature and lost output even when nothing has electrically failed
  • Physical damage visible in RGB that thermal alone would miss: cracked glass, delamination, connector corrosion, vegetation shading a corner of a table

The catch with a flyover is cadence. Run annually, it's a snapshot. It won't catch the string that trips in March if the flight is in October. That's the tradeoff for resolution: you get cell-level detail across the whole site, once a year, instead of continuous coarse-grained data.

Where the two overlap, and where they don't

In practice the two methods aren't really competing for the same job. SCADA is your early-warning system for anything that fully fails. A flyover is how you find everything that's quietly losing you production without ever failing hard enough to trip a sensor, and it's how you turn "something's wrong somewhere in this 40-acre block" into a ranked list of which tables to send a crew to first.

An O&M team running on SCADA alone tends to chase hard failures and miss the slow bleed: soiling on tables that never alarm, a bypass diode that's been dead for a season, hot cells creeping toward failure. An O&M team running on an annual flyover alone has excellent cell-level visibility once a year and nothing in between. Most sites worth monitoring closely end up running both, with the flyover doing the job SCADA structurally can't: resolving a whole-site problem down to the panel.

That's the gap Panel Soiling is built to close: a paired RGB and thermal flyover delivered as a ranked findings dossier, so your crews know which tables to clean or inspect first instead of walking every row with a handheld camera to find out what your DAS already told you was wrong somewhere.

If your SCADA alarms keep pointing at a string without telling you which panel on it to fix, get in touch about scheduling a flyover for your next inspection window.